CASE STUDIES

Real projects. Real results. See how HOAK Labs has helped clients across Pakistan reduce downtime and recover critical systems.

500+

Devices Repaired

98%

First-Fix Success Rate

48hr

Average Turnaround

PKR 50M+

Client Savings Generated

Proven Results

Each project represents a customer whose production was restored, costs were saved, and trust was earned.

VFD RepairTextile Manufacturing — Karachi

Siemens MICROMASTER 440 Fleet Overhaul

A major textile mill had 12 Siemens MICROMASTER 440 VFDs failing intermittently, causing frequent production stoppages and quality defects in yarn production.

HOAK Labs performed full diagnostic analysis identifying power capacitor degradation and IGBT driver board faults as the root cause. All 12 units were systematically overhauled over a scheduled maintenance window.

SiemensVFDTextilePreventive Maintenance

100% success rate. Production downtime reduced by 85%. Estimated savings of PKR 2.4M per year in lost production.

Duration3 weeks
ValuePKR 1.8M project
PLC UpgradeFood & Beverage — Karachi Industrial Area

Legacy PLC Migration — Food Processing Plant

An aging Allen-Bradley PLC-5 system controlling a high-speed filling line was becoming unreliable with spare parts no longer available. The client needed a migration path without halting production.

HOAK Labs developed a phased migration plan to CompactLogix platform, with complete program translation, I/O remap, and parallel testing. The cutover was executed during a planned shutdown weekend.

Allen-BradleyPLC UpgradeFood ProcessingMigration

Seamless migration completed in 54 hours. System uptime improved from 87% to 99.2%. Full remote monitoring capability added.

Duration6 weeks
ValuePKR 3.2M project
Servo DrivePackaging — Lahore

Multi-Axis Servo Drive Recovery

A packaging machine manufacturer had a critical Fanuc servo drive system fail, affecting a customer installation. The original supplier quoted 8-week lead time for replacement.

HOAK Labs received the failed drives, performed component-level diagnosis identifying a failed power stage and corrupted parameter memory. Repair was completed within 4 days including full load testing.

FanucServo DrivePackagingEmergency Repair

Machine operational within 5 days vs 8-week replacement. Client saved 90% on repair vs replacement cost. Machine has run 14 months without fault.

Duration4 days
ValuePKR 280K vs PKR 2.8M replacement
Generator ControlIT Infrastructure — Karachi

Data Centre Synchronizing Controller Repair

A data centre's DSE 8610 synchronizing controller failed during maintenance, leaving the facility relying on a single generator without proper load sharing and synchronization protection.

Emergency on-site attendance within 2 hours. DSE module diagnosed with CPU board failure. Component replaced and system recalibrated and recommissioned on-site.

DSEGeneratorData CentreEmergency

Full redundancy restored within 6 hours of initial call. Zero data loss or service interruption. Annual maintenance contract established.

Duration6 hours
ValueEmergency response
HMI RepairCement — Hub Industrial Zone

Siemens TP2200 Comfort Panel Restoration

Cement plant's primary process HMI suffered touchscreen failure and corrupted project data. The OEM quoted 16 weeks delivery for a replacement panel at high cost.

HOAK Labs replaced the damaged touchscreen overlay, recovered and re-flashed the project data from backup, and performed full functional testing against the SCADA system.

SiemensHMICementScreen Repair

Panel fully operational within 10 days. Cost was 30% of replacement price. Customer data fully recovered.

Duration10 days
ValuePKR 320K vs PKR 1.1M replacement
DC DriveSteel Processing — Karachi

DC Drive Fleet Maintenance — Steel Mill

A steel processing facility had 8 aging DC drives showing signs of deterioration with no local repair capability and long overseas repair times.

HOAK Labs established a preventive maintenance schedule, cleaning, inspecting, and recalibrating all drives. Two units required armature firing circuit board repairs.

DC DrivesSteelPreventive MaintenanceFleet

All drives restored to optimal performance. Zero unplanned failures in subsequent 12 months. Annual contract signed.

DurationOngoing contract
ValueAnnual maintenance program

Your Success Story Starts Here

Join hundreds of satisfied clients who trust HOAK Labs to keep their operations running.

Start Your Project →